Business value
This feature gives customers two new schedule modes to choose from: Fixed duration/Effort driven, and Fixed units/Effort driven. These two schedule modes force effort to remain constant when extra resources are assigned (or removed) from a task in addition to keeping duration or units (depending on which mode is chosen) constant.
Feature details
Project for the web has three schedule modes: Fixed effort, Fixed duration, and Fixed units. All three schedule modes keep the specified field (effort, duration, or units) constant when you make changes that trigger a recalculation. This feature adds two schedule modes: Fixed duration/Effort driven and Fixed units/Effort driven. In these schedule modes, when you add or remove a resource from a task, the effort stays constant along with the duration or units, depending on the schedule mode you choose.
Geographic areas
Visit the Explore Feature Geography report for Microsoft Azure areas where this feature is planned or available.
Language availability
Visit the Explore Feature Language report for information on this feature's availability.
Additional resources
Project effort tracking (docs)
Scheduling modes (learn)
Aug 31, 2024