This article explains how to view, manage, and approve planned orders.
View and manage planned orders
You can view and manage planned orders on any planned orders list page. Go to one of the following places, depending on the type of planned orders that you want to work with:
- Master planning > Workspaces > Master planning
- Master planning > Master planning > Planned orders
- Production control > Production orders > Planned production orders
- Procurement and sourcing > Purchase orders > Planned purchase orders
- Inventory management > Inbound orders > Planned transfers
- Inventory management > Outbound orders > Planned transfers
View and edit the status of planned orders
Use the Status field of each planned order to track your progress or change how a planned order is processed. The following Status values are available:
- Unprocessed – When master planning generates planned orders, it assigns this status. Planned orders with this status are deleted during the next planning run.
- Completed – This status indicates that the planned order is completed. If you decide not to firm a planned order, you can manually change its status to Completed. The system treats the Unprocessed and Completed statuses in the same way.
- Approved – This status indicates that the planned order is approved for firming. If you want to firm a planned order, change its status to Approved. If you want to keep the edits that you made to a planned order, or if you're planning to firm a planned order, change its status to Approved. Planned orders with a status of Approved are considered fixed and expected supply by master planning. Therefore, they're not modified or deleted during later master planning runs. To achieve this behavior, the planning logic copies planned orders with a status of Approved from the old plan version to the new plan version during master planning. Planned orders with a status of Approved are considered supply only within the specific master plan.
To change the status of a single planned order, open any planned orders list page, open the order, and then follow one of these steps:
- On the General FastTab, change the value of the Status field.
- On the Action Pane, on the Planned order tab, in the Process group, select Change status.
- On the Action Pane, select Approve to mark the order as approved.
To change the status of several planned orders at the same time, open any planned orders list page, select the check box for each order that you want to change, and then follow one of these steps:
- On the Action Pane, on the Planned order tab, in the Process group, select Change status.
- On the Action Pane, select Approve to mark the orders as approved.
Approve planned orders
Approving planned orders is an optional step in the process of creating a firmed order from a planned order.
The following illustration shows how you can use the Status value that is assigned to each planned order to implement an approval workflow. To implement an approval process, manually adjust the Status value for each planned order as described in the previous section.

Tip
We recommend that you approve any modified planned orders. Otherwise, the edits are ignored and overwritten by the next planning run.