ACWP is the Actual Cost of Work Performed up to the project status date or today's date.
For a <Task>, <ACWP> is the costs incurred for work already done on a task.
For a <Resource>, it is the sum of ACWP values for all of a resource's assignments.
For an <Assignment>, it is the costs incurred for work already performed by a resource on a task.
Element Properties
| Property | Value |
|---|---|
| Data Type | Float |
| Minimum Occurrences | 0 |
| Maximum Occurrences | 1 |
| Default Value | N/A |
| Abstract | False |
| Nillable | False |
| Element Constraints | N/A |
Parent Elements
See Also
XML Schema for the <Task> Element
XML Structure for the <Task> Element
XML Schema for the <Resource> Element
XML Structure for the <Resource> Element
XML Schema for the <Assignment> Element
XML Structure for the <Assignment> Element