CV is also called cost variance. In general, CV is the difference between how much it should have cost and how much it has actually cost to achieve the current level of completion up to the status date or today's date.
For a <Task>, <CV> is the cost variance applied to a task.
For a <Resource>, it is the cost variance applied to a resource.
For an <Assignment>, it is the cost variance applied to an assignment.
Element Properties
| Property | Value |
|---|---|
| Data Type | Float |
| Minimum Occurrences | 0 |
| Maximum Occurrences | 1 |
| Default Value | N/A |
| Abstract | False |
| Nillable | False |
| Element Constraints | N/A |
Parent Elements
See Also
XML Schema for the <Task> Element
XML Structure for the <Task> Element
XML Schema for the <Resource> Element
XML Structure for the <Resource> Element
XML Schema for the <Assignment> Element
XML Structure for the <Assignment> Element