Gets or sets the unit of measure in which the scheduled duration of a task is displayed in Project.
Namespace: WebSvcStatusing
Assembly: ProjectServerServices (in ProjectServerServices.dll)
Syntax
'Declaration
Public Property TASK_SCHED_DUR_FMT As Integer
Get
Set
'Usage
Dim instance As ProjectDataSet.TaskRow
Dim value As Integer
value = instance.TASK_SCHED_DUR_FMT
instance.TASK_SCHED_DUR_FMT = value
public int TASK_SCHED_DUR_FMT { get; set; }
Property value
Type: System.Int32
Remarks
It takes the following values:
Int Value |
Enum Value |
Description |
Estimated |
|---|---|---|---|
3 |
Minute |
Minutes |
No |
4 |
EMinute |
Elapsed minutes |
No |
5 |
Hour |
Hours |
No |
6 |
EHour |
Elapsed hours |
No |
7 |
Day |
Days |
No |
8 |
EDay |
Elapsed days |
No |
9 |
Week |
Weeks |
No |
10 |
EWeek |
Elapsed weeks |
No |
11 |
Month |
Months |
No |
12 |
EMonth |
Elapsed months |
No |
19 |
Percent |
Percentage |
No |
20 |
EPercent |
Elapsed percentage |
No |
21 |
Null |
No value |
No |
37 |
EstHour |
Estimated hours |
Yes |
38 |
EEstHour |
Elapsed estimated hours |
Yes |
39 |
EstDay |
Estimated days |
Yes |
40 |
EEstDay |
Elapsed estimated days |
Yes |
41 |
EstWeek |
Estimated weeks |
Yes |
42 |
EEstWeek |
Elapsed estimated weeks |
Yes |
43 |
EstMonth |
Estimated month |
Yes |
44 |
EEstMonth |
Elapsed estimated months |
Yes |
51 |
EstPercent |
Estimated percentage |
Yes |
52 |
EEstPercent |
Elapsed estimated percentage |
Yes |
53 |
None |
No display format |
Yes |