Indicates whether the end of completed portions of tasks scheduled to have been completed before the status date, but begun late, should be moved up to the status date.
<MoveCompletedEndsForward>
BooleanValue
</MoveCompletedEndsForward>
Parent Elements
Occurrences
Minimum: 0 Maximum: 1 |
Text Value
A text value of type boolean is required.
Value |
Description |
|---|---|
0 |
False |
1 |
True |
Remarks
The MoveCompletedEndsForward element has a rounding error. The internal work value has eight digits; the work value loses 0.001 seconds for every minute, causing a rounding error.