Specifies finite loading of a work center or machine center.
This table enables you to set up resource that you regard as critical and mark them to accept a finite load instead of the default infinite load that other resources accept.
A critical area can be a work center or machine center that you have identified as a bottleneck and would like to establish a limited (finite) load for.
Note
Operations on work or machine centers set up as constrained resources will always be planned serially. This means that ever if a constrained resource has multiple capacities (the Capacity field on the work or machine center card is higher than 1), then those capacities can only be planned in sequence, not in parallel as would be the case if the work or machine center was not set up as a constrained resource.
List of Fields in the Table
The following table lists the fields in this table.
| Prod. Order Need Qty. for Plan Field, Capacity Constrained Resource Table |
Manufacturing |
| Critical Load % Field, Capacity Constrained Resource Table |
Manufacturing |
| Prod. Order Need Qty. Field, Capacity Constrained Resource Table |
Manufacturing |
| Name Field, Capacity Constrained Resource Table |
Manufacturing |
| Dampener (% of Total Capacity) Field, Capacity Constrained Resource Table |
Manufacturing |
| Capacity No. Field, Capacity Constrained Resource Table |
Manufacturing |
| Work Shift Filter Field, Capacity Constrained Resource Table |
Manufacturing |
| Work Center No. Field, Capacity Constrained Resource Table |
Manufacturing |
| Capacity (Effective) Field, Capacity Constrained Resource Table |
Manufacturing |
| Capacity Type Field, Capacity Constrained Resource Table |
Manufacturing |
| Work Center Load Qty. Field, Capacity Constrained Resource Table |
Manufacturing |
| Date Filter Field, Capacity Constrained Resource Table |
Manufacturing |
| Work Center Load Qty. for Plan Field, Capacity Constrained Resource Table |
Manufacturing |
| Prod. Order Need Qty. for Plan Field, Capacity Constrained Resource Table |
Manufacturing |
| Critical Load % Field, Capacity Constrained Resource Table |
Manufacturing |
| Prod. Order Need Qty. Field, Capacity Constrained Resource Table |
Manufacturing |
| Date Filter Field, Capacity Constrained Resource Table |
Manufacturing |
| Name Field, Capacity Constrained Resource Table |
Manufacturing |
| Dampener (% of Total Capacity) Field, Capacity Constrained Resource Table |
Manufacturing |
| Capacity No. Field, Capacity Constrained Resource Table |
Manufacturing |
| Work Shift Filter Field, Capacity Constrained Resource Table |
Manufacturing |
| Work Center Load Qty. for Plan Field, Capacity Constrained Resource Table |
Manufacturing |
| Work Center No. Field, Capacity Constrained Resource Table |
Manufacturing |
| Capacity (Effective) Field, Capacity Constrained Resource Table |
Manufacturing |
| Capacity Type Field, Capacity Constrained Resource Table |
Manufacturing |
| Work Center Load Qty. Field, Capacity Constrained Resource Table |
Manufacturing |
See Also
Reference
Finite Loading
Critical Load %
Capacity
Other Resources
How to: Display the Load on Work Centers